Feed In Tariffs

The information site for the forthcoming guaranteed payments for renewable heat

FAQs

How does the metering need to be configured?

The system design showing the meters will need to be submitted to Ofgem for verification.

Chapter 7 of the government’s RHI announcement says

Verification

For all participants seeking accreditation for the RHI, Ofgem will require submission of a schematic diagram of the plant. The schematic will need to include details of the plant and the location of meters and associated components. Where additional capacity/plant is added or there are any changes to the metering arrangements participants will need to provide a revised schematic diagram (and possibly other information) to Ofgem showing the position of the additional generation facilities and any changes to metering.

In certain circumstances, Ofgem will require an independent site report to be undertaken by a competent person to verify the schematic diagram. The RHI regulations and Ofgem guidance will set out where this applies. The cost of providing this information will be borne by the participant.